PROVINCETOWN AIRPORT COMMISSION
MONTHLY MEETING
PROVINCETOWN MUNICIPAL AIRPORT
WEDNESDAY, 1 OCTOBER 2003
The
Provincetown Airport Commission held their monthly meeting on Wednesday, 1
October 2003 at the Provincetown Municipal Airport Conference Room. Those in attendance were Richard Silva,
Chairman, Steve Page, Vice Chairman, Steve Tait, Treasurer, Joan Drysdale,
Secretary, and Leonard Alberts, M. D., Commissioners, Jason Stover (who arrived
at 5:38) alternate Commissioner, Butch Lisenby, Airport Manager, and Steve
Flecchia, consultant, Edwards & Kelcey.
The
meeting was called to order by Chairman Silva at 5:32 P.M.
I. RUNWAY IMPROVEMENT PROJECT
UPDATE
Some
punch list items still remain incomplete.
The contractor has been notified and is aware of the situation. Efforts will be made over the next few weeks
to complete the remaining items.
II. PARKING APRON/SECURITY
IMPROVEMENTS PROJECT UPDATE
The
General Contractor’s contracts and grants approved at Sept. 8, 2003 Board of
Selectmen’s meeting. The MAC grant was
approved on Sept. 17, 2003. The fully
executed contract has been sent to the contractor. Due to timing issues this fall, construction is tentatively
scheduled to begin early spring 2004.
This is primarily due to the preparation for environmental and erosion
control and the need of the Cape Cod Commission to have a minimum of two weeks
notification for pre-construction inspection.
III. AIRPORT MASTER PLAN
The
Commission needs to update the current plan, which may take several years. There are environmental issues.
IV. PARK SERVICE MOA UPDATE
It
is currently in limbo. Some items have
been ironed out. The major problem is
our right to be an airport as long as we choose to be. We feel we have the right, the U. S. Dept.
of Interior, Cape Cod National Seashore disagrees.
V. AIRPORT CONSULTANT SELECTION
The current three-year term expires in
December. Lisenby will send out
requirements and RFP notices.
Page
2 of 2- Airport Commission - 10.1.03
VI.
PAYMENT VOUCHERS
1. Edwards and Kelcey #1 Apron Project Invoice $
130,000.00
MOTION: TO
PAY EDWARD AND KELCEY THE SUM OF $130,000.00
UPON
RECEIPT OF THE GRANTS.
MOVED: LEONARD ALBERTS SECOND: STEVE
PAGE
VOTE: 4
YES 0
NO 0
ABSTENTIONS
2. Edwards and Kelcey #2 Apron Project Invoice $ 1,750.00
MOTION: TO
PAY EDWARD AND KELCEY THE SUM OF $130,000.00
UPON
RECEIPT OF THE GRANTS.
MOVED: LEONARD ALBERTS SECOND: STEVE
TAIT
VOTE: 4
YES 0
NO 0
ABSTENTIONS
3. Ken Lambert for mowing of approach grass $ 1,545.00
MOTION: TO
PAY KEN LAMBERT THE SUM OF $1,545.00
FOR
MOWING OF THE APPROACH GRASS
MOVED: LEONARD ALBERTS SECOND: STEVE
TAIT
VOTE: 4
YES 0
NO 0
ABSTENTIONS
VII. OTHER BUSINESS
The
alternate commissioner, Jason Stover, was sworn in today. Michelle Haynes of Cape Air informed the
commissioners that the Providence site is now closed with hopes to re-open in
the spring. The market has eroded, but
Provincetown is safe and will not be closed.
She also stated that there have been major cuts in New England.
VIII. MINUTES
There
were none.
The
next meeting will be held on 5 November 2003.
MOTION: TO
ADJOURN
MOVED: LEONARD ALBERTS SECOND: STEVE
TAIT
VOTE: 4
YES 0
NO 0
ABSTENTIONS
The
meeting was closed at 6:04 P. M.
Respectfully
submitted,
Joan
M. Drysdale, Commissioner
Recording
Secretary
APPROVED:
NOV 5, 2003