PROVINCETOWN AIRPORT COMMISSION
17 DECEMBER 2002
The Provincetown Airport
Commission met for its stated meeting on Tuesday, 17 December 2002 at the
Provincetown Municipal Airport Conference Room.
Those in attendance were:
Richard Silva Commissioner
Steve Tate Commissioner
Steve Page Commissioner
Joan M. Drysdale Commissioner
Butch Lisenby Airport Manager
Steve Flecchia Consultant,
Edwards & Kelcey
Heath Gatlin was absent
with permission.
The meeting was called to
order at 5:43 by Chairman Silva.
I. AIRPORT SECURITY
Enclosure for security
construction begun; discovered not enough room was allotted. Manager will allow expansion. There are questions that will need answers: there appears not to be enough room for all
the necessary equipment; the screening area is too small; TSA will not do
trailer set up themselves; they are looking for middleman to do the work; then
the payment schedule will be from TSA to the middleman to the Airport.
II. RUNWAY IMPROVEMENT PROJECT UPDATE
Fruean Utilities
completed relocation work associated with the Localizer, DME, NDB, Glide Slope,
and AWOS NAVAIDS.
Fruean Utilities
began the installation of the MALSF (approach lights) and is scheduled to
complete the remaining approach light work by Dec. 24, 2002 (weather
permitting).
Other remaining major
construction items: R/W 25 REILS, R/W 7 and 25 PAPI’s to be completed by Jan.
14, 2003.
ILS (Localizer and
Glide Slope) and DME ready for flight check; waiting on airway facilities
flight check.
AWOS Cloud-Height,
Rain Gauge, Temperature, Barometric Pressure, and Dew Point instruments back in
service; airway facilities working out problems with wind tower and visibility
sensor.
Sixty-seven day
contract extension submitted under a Change Order (#3) for review. Original project completion date 11/8/02;
revised completion date 1/14/03. Some
spring restoration work required.
Summary of FAA
NAVAIDS:
Localizer: Complete (waiting for flight check)
DME: Complete
(waiting for flight check)
Glide Slope: Complete (waiting for flight check)
NDB: Complete
Approach lights: Underway
(scheduled to be completed by
12/24/02)
AWOS Completed
except for problem with wind tower
and visibility sensor
REILS Incomplete
(scheduled to be completed by 1/14/03)
PAPI’s Incomplete
(scheduled to be completed by 1/14/03)
If the FAA does not accept
and agree to Change Order #3, there will be a money issue which may lead to
liquidated damages.
III. TERMINAL HVAC UPDATE
Status quo - good days and
bad days with system. Have reached end
of agreement with Black and Veatch. The
rattle was damper above bathrooms - has been removed. Bath and conference room temperatures run cold. Black and Veatch to see what can be done.
IV. PAYMENT VOUCHERS
1. LAWRENCE/LYNCH CORP. $643,046.23
MOTION: TO
PAY LAWRENCE/LYNCH THE SUM OF $643,046.23
UPON
RECEIPT OF FUNDING.
MOVE: STEVE
TATE
SECOND: STEVE
PAGE
VOTE: 3 YES 0 NO 0
ABSTENTIONS
2. EDWARDS & KELCEY $ 30,025.69
MOTION: TO
PAY EDWARDS & KELCEY THE SUM OF $30,025.69
UPON
RECEIPT OF FUNDING.
MOVE: STEVE
TATE
SECOND: STEVE
PAGE
VOTE: 3 YES 0 NO 0
ABSTENTIONS
3. KEN WHEELER, ELECTRICIAN $ 1,025.00
MOTION: TO
PAY KEN WHEELER THE SUM OF $1,025.00 FOR
ONGOING
PARTS AND LABOR FOR GENERAL AIRPORT
REPAIR
AND REPLACEMENT
MOVE: JOAN
M. DRYSDALE
SECOND: STEVE
PAGE
VOTE: 3 YES 0 NO 0
ABSTENTIONS
4. CAPE COD TRUCK $
853.39
MOTION: TO
PAY CC TRUCK THE SUM OF $853.39 FOR REPAIR
AND
MAINTENANCE OF AIRPORT DUMP TRUCK
MOVE: JOAN
M. DRYSDALE
SECOND: STEVE
TATE
VOTE: 3 YES 0 NO 0
ABSTENTIONS
5. EPSILON ASSOCIATES $
5,659.43
MOTION: TO
PAY EPSILON ASSOC. THE SUM OF $5,659.43 FOR
MONITORING
THE ONGOING RECONSTRUCTION PROJECT
MOVE: STEVE
TATE
SECOND: STEVE
PAGE
VOTE: 3 YES 0 NO 0
ABSTENTIONS
V. OLD BUSINESS
Lisenby
announced that Dr. Leonard Alberts has been appointed as a full member of the
commission and will return on 1/1/03.
He also stated that Dr. Alberts has a conflict with Tuesday meetings as
he has to work till 8 on that evening.
The commissioners present
determined that they would move the regular meeting date to the second
Wednesday of the month.
VI. MINUTES
The minutes of the
meetings of Sept. 18th and Nov. 26th were presented for consideration.
MOTION: TO APPROVE THE MINUTES OF SEPT. 18TH
AND NOV. 26TH AS
PRESENTED.
MOVE: STEVE TATE
SECOND: STEVE PAGE
VOTE: 3
YES 0
NO 0
ABSTENTIONS
The next meeting will be
held on 8 January 2003.
The meeting was adjourned
by unanimous voice vote at 6:16 P.M.
Respectfully submitted,
Joan M. Drysdale,
Commissioner
Recording Secretary
APPROVED: MAR 26, 2003